TVA early, under budget on Sevier gas plant

In this mention

TVA completed the $790 million John Sevier Combined Cycle Gas Plant near Rogersville, Tennessee, a month ahead of schedule and $30 million under budget. The 880-megawatt natural gas plant began commercial operation and will replace part of TVA's nearby coal plant, serving approximately 500,000 homes. This is the fifth combined cycle gas plant TVA has acquired or built in five years.

Read the full article at Times Free Press

Reposted 2 times in the following media sources

Original clipping

Full transcript

TVA early, under budget on Sevier gas plant

May 2, 2012

by

Dave Flessner

Despite cost overruns and delays in its nuclear power program, TVA finished a natural gas power plant this week a month ahead of schedule and $30 million under budget.

The $790 million John Sevier Combined Cycle Gas Plant, which began generating commercial power Monday, will replace part of TVA's nearby coal plant near Rogersville, Tenn. The 880-megawatt plant is the fifth combined cycle gas plant TVA has bought or built in the past five years and will produce enough power for about 500,000 homes.