Skip to content

Press Mention Charlotte Business Journal December 25, 2013

SACE Referenced PDF clipping

Groups press for massive solar project with Duke Energy plant

In this mention

Environmental groups Southern Alliance for Clean Energy and Coastal Conservation League filed comments with South Carolina regulators urging Duke Energy Carolinas to build a 375-megawatt solar farm alongside its proposed 750-megawatt natural gas plant in Anderson County. Duke Energy disputes the proposal as unrealistic, citing the lack of commercial solar projects of that scale in the nation and the land requirements. The dispute will be addressed at a South Carolina Public Service Commission hearing scheduled for January 7.

Original clipping

Full transcript

Two environmental groups say Duke Energy Carolinas should be required to build a solar farm with a capacity as large as 375 megawatts as part of its proposed 750-megawatt natural gas plant in South Carolina.

In filings with S.C. regulators, the Southern Alliance for Clean Energy and the Coastal Conservation League also argue that Duke Energy Carolinas should be allowed to share capacity with Duke Energy Progress, delaying the need for the plant in Anderson County.

But Duke says a solar project that large is simply unrealistic. Responding to the groups, Janice Hager, Duke's vice president of resource planning, notes there is no commercial solar project of that size in the nation.

And she says building such a project would require 2,625 acres, compared with 20 acres for the proposed Lee Combined Cycle Plant.

Hager also disputes a highly technical argument the groups make that Duke has overestimated how much reserve power the company needs, leading it to want to build Lee before it is necessary.

The dispute will be among the issues aired at a hearing the S.C. Public Service Commission will hold on the project Jan. 7.