Press Mention Tampa Bay Times (FL) October 13, 2013

SACE Referenced PDF clipping

Florida PSC's OK of Settlement Will End Inquiries Into Duke Energy Nuke Plants

In this mention

The Florida Public Service Commission approved a settlement regarding Duke Energy's failed nuclear projects at Crystal River and Levy County, which cost customers over $3 billion. The article details how Duke/Progress Energy mismanaged a steam generator replacement project and an abandoned new reactor construction, with the settlement preventing full public disclosure of the failures. SACE's unsuccessful legal challenge to the nuclear advance fee law is mentioned in the context of the settlement's inevitability.