No More Corporate Welfare at Taxpayer Expense for Plant Vogtle Nuclear Project

Guest Blog | August 29, 2018 | Press Releases

Organizations demand investigation into billions more in federal nuclear loan guarantees

Contacts:
Debbie Dooley, Atlanta Tea Party and Conservatives for Energy Freedom, 678-761-6725
John Hitchins, Georgians for Energy Freedom, 404-934-3575
Tim Judson, NIRS, 301-270-6477 x2
Jennifer Rennicks, Southern Alliance for Clean Energy, 865-235-1448

 

Atlanta, Ga. (August 29, 2018) – Today a coalition of taxpayer and consumer watchdog organizations representing both conservative and progressive members requested that the U.S. House and Senate Budget Committees investigate the troubled Vogtle nuclear expansion project in Georgia and the risks to U.S. taxpayers before the Department of Energy (DOE) finalizes an additional $3.7 billion in taxpayer-backed federal loan guarantees for this troubled project. The groups filed a detailed letter last week with Energy Secretary Rick Perry highlighting that costs for the only remaining new nuclear construction project in the country had increased yet again, this time by an additional $2.3 billion, just months after the previous multi-billion dollar cost increase was approved by the Georgia Public Service Commission (PSC). The DOE has yet to reply. The Vogtle expansion’s original project costs, originally estimated at $14 billion, has now doubled, as has the construction schedule.

“True Conservatives don’t believe in bailing out corporations for bad decisions. The Vogtle Project has turned into a ‘Nuclear Solyndra’ that puts tax payer dollars at risk,â€ said Debbie Dooley, President of the Atlanta Tea Party and Conservatives for Energy Freedom who delivered letters to Georgia’s representatives on both the U.S. House and Senate Budget Committees today. “I urge you to be good stewards of tax payer dollars by investigating the Vogtle Project and encouraging the Department of Energy to turn down the Federal Loan Guarantee request by the Vogtle partners.â€

In an effort to buoy the project, DOE announced conditional approval last September of an additional $3.7 billion in federal taxpayer-backed nuclear loan guarantees to three of the Vogtle project partners: $1.67 billion to Southern Co.’s Georgia Power, $1.6 billion to Oglethorpe Power Corp., and $415 million to the Municipal Electric Authority of Georgia (MEAG). These proposed loans are on top of the $8.3 billion in loan guarantees that utility project partners previously secured.

“Doling out even more corporate welfare at taxpayers’ expense for a failing nuclear project in Georgia is outrageous,” said Sara Barczak, regional advocacy director with the Southern Alliance for Clean Energy (SACE).

The coalition’s letter to DOE mentions that construction is only approaching 50 percent completion nine years into the project, and the actual completion of Vogtle is increasingly uncertain – all increasing the risk of default to U.S. taxpayers. Coalition members encouraged Secretary Perry to withdraw consideration of the loan guarantees, and if he were to proceed, requested that significantly higher credit subsidy fees be assessed.

“Like over fifty nuclear reactors before them, the Vogtle reactor project shows every sign of failure and, ultimately, being canceled. It’s like watching a slow-moving train wreck,â€ said Tim Judson, executive director of the Nuclear Information & Resource Service (NIRS). “Wall Street has downgraded all of the utilities involved in this project since the latest multi-billion dollar cost increase, and Vogtle’s largest customer says ‘a decision to continue cannot be justified on any rational basis.’ U.S. taxpayers are already on the hook for $8.3 billion in loans for Vogtle. DOE needs to put on the breaks before flushing another $3.7 billion down the drain.â€

“Lack of accountability has led Plant Vogtle to become a money pit. With no end of construction in sight and costs continuing to soar by the billions, this project has become the definition of fiscal irresponsibility,â€ said John Hitchins with Georgians for Energy Freedom. “Difficult decisions will have to be made, but Georgia ratepayers and federal taxpayers deserve to be protected. We urge you to discontinue federal loan guarantees until we know the future of Vogtle.â€

Additional background:

Since the original $8.3 billion in loan guarantees were offered in 2010, the Southern Alliance for Clean Energy (SACE) filed extensive Freedom of Information Act (FOIA) requests and went to court twice to force DOE to unearth important details on the risks posed to U.S. taxpayers if the Plant Vogtle nuclear project should default — a reality that plays a large role in the nuclear industry’s history. Read more here.

 

###